Standard Notes (Design)
|
Date | Description |
---|---|
09.24.2014 | 105-110 PAVEMENT SWEEPING: Sweep paved areas that were used by construction traffic before opening these areas to public traffic. Sweep all newly constructed pavement no more than 24 hours before a scheduled final inspection. Use a vacuum or pick-up type sweeper to perform this work. |
09.24.2014 | 105-200 UTILITY COORDINATION: A utility coordination meeting is required. (This note is intended for use on projects where numerous utility conflicts and/or relocations are set to occur. Examples include urban reconstruction, construction on new alignment, any projects that include widening, appropriate emergency projects & projects requested by the District or Utilities Engineer.) |
09.24.2014 | 107-100 LAWS TO BE OBSERVED: All or a portion of this project lies within the exterior boundaries of an Indian Reservation. Review laws and ordinances pertaining to the work contained within the boundaries of the reservation. |
08.26.2015 | 107-111 RAILROAD PROTECTIVE LIABILITY INSURANCE: This project crosses the Dakota, Missouri Valley & Western Railroad Company at RP ______. The type of work that will be performed within the railroad right of way is _________________. Direct inquiries regarding protective liability insurance to: JEFF WOOD Executive Vice President Dakota, Missouri Valley & Western Railroad, Inc. 3501 East Rosser Avenue Bismarck, ND 58501 701-223-9282 off. jwood@dmvwrr.com Obtain information regarding crossing number ___________ from the Federal Railroad Administration website: http://safetydata.fra.dot.gov/Officeofsafety/ Use this note when crossing the Dakota, Missouri Valley & Western Railroad. (You will need to contact the Planning division to obtain the RP number and the crossing number. Examples of types of work: Paving, Seal Coat, Striping, Earthwork, Base Work, etc.) |
09.06.2023 | 107-112 RAILROAD PROTECTIVE LIABILITY INSURANCE: This project crosses the Canadian Pacific Kansas City Railway at RP ______. The type of work that will be performed within the railroad right of way is _________________. Direct inquiries regarding protective liability insurance to: BRIAN OSBORNE Manager Public Works Canadian Pacific Kansas City Railroad 120 South 6th Street, Suite 700, Minneapolis, MN 55402 612-330-4555 off. brian_osborne@cpkcr.ca Obtain information regarding crossing number ___________ from the Federal Railroad Administration website: http://safetydata.fra.dot.gov/Officeofsafety/ Use this note when crossing the Canadian Pacific Kansas City Railroad. (You will need to contact the Planning division to obtain the RP number and the crossing number. Examples of types of work: Paving, Seal Coat, Striping, Earthwork, Base Work, etc.) |
12.07.2022 | 107-113 RAILROAD PROTECTIVE LIABILITY INSURANCE: This project crosses the Northern Plains Railroad at RP ______. The type of work that will be performed within the railroad right of way is _________________. Direct inquiries regarding protective liability insurance to: Jesse Chalich President Northern Plains Railroad P.O. Box 38 Fordville, ND 58231 701-229-3444 off. jesse_chalich@nprail.com Obtain information regarding crossing number ___________ from the Federal Railroad Administration website: http://safetydata.fra.dot.gov/Officeofsafety/ Use this note when crossing the Northern Plains Railroad. (You will need to contact the Planning division to obtain the RP number and the crossing number. Examples of types of work: Paving, Seal Coat, Striping, Earthwork, Base Work, etc.) |
12.07.2022 | 107-114 RAILROAD PROTECTIVE LIABILITY INSURANCE: This project crosses the Red River Valley and Western Railroad Company at MP ______. The type of work that will be performed within the railroad right of way is _________________. Direct inquiries regarding railroad protective liability insurance to: Kristin Nicholson VP of Finance & Administration Red River Valley and Western Railroad P.O. Box 608 Wahpeton, ND 58074 701-642-8257 off. kristin.nicholson@rrvw.net Obtain information regarding crossing number ___________ from the Federal Railroad Administration website: http://safetydata.fra.dot.gov/Officeofsafety/ Use this note when crossing the Red River Valley and Western Railroad. (You will need to contact the Planning division to obtain the MP number and the crossing number. Examples of types of work: Paving, Seal Coat, Striping, Earthwork, Base Work, etc.) |
12.15.2015 | 107-115 RAILROAD PROTECTIVE LIABILITY INSURANCE: This project crosses the BNSF Railway Company at RP ______. The type of work that will be performed within the railroad right of way is _________________. Direct inquiries regarding protective liability insurance to: Rosa Martinez Marsh USA Inc. 4400 Comerica Bank Tower 1717 Main Street Dallas, TX 75201-7357, USA 214-303-8519 Rosa.M.Martinez@marsh.com Obtain information regarding crossing number ___________ from the Federal Railroad Administration website: http://safetydata.fra.dot.gov/Officeofsafety/ Use this note when crossing the Burlington Northern Santa Fe Railroad. (You will need to contact the Planning division to obtain the RP number and the crossing number. Examples of types of work: Paving, Seal Coat, Striping, Earthwork, Base Work, etc.) |
01.02.2018 | 107-300 CONSTRUCTION TRAFFIC ACCESS: Access areas within the right of way only at interchanges. The Engineer may allow temporary access at other locations. To obtain temporary access, provide an access plan containing the following information:
Note to be used for Interstate projects. |
10.09.2014 | 107-310 CONSTRUCTION TRAFFIC MEDIAN CROSSOVERS: During daylight hours, material may be hauled over the roadway used by public traffic. If the Contractor intends to perform this action, the following conditions must be met:
All work necessary to construct and maintain crossovers, provide traffic control, and to restore the area to its pre-existing condition must be completed at no additional cost to the Department. Note is for use on divided highways. |
09.26.2014 | 107-500 PAVEMENT SWEEPING: Sweep the roadway adjacent to the construction area at the end of each day. Utilize a vacuum or pickup type sweeper. |
09.26.2014 | 107-900 THREE AFFILIATED TRIBES BIA COORDINATION: Coordinate work on lands held in trust by the Bureau of Indian Affairs (BIA), allotted and tribally owned trust land, through the Environmental/Compliance Officer. Contact: Jeff Desjarlais Environmental/Compliance Officer, Ft. Berthold (701) 627-4707, ext. 244 Coordinate work regarding materials sources, staging areas, office locations, and other activities that are not expressly detailed in the contract documents. Note to be used on all projects that include work on the Fort Berthold Reservation. |
08.02.2016 | 108-100 WEEKLY PLANNING & REPORTING MEETING: A weekly planning and reporting meeting is required. (This note is intended for use on projects where a weekly meeting is required. The Specifications require the Engineer in the field to provide a list of invitees to the Contractor at the Pre-Construction Meeting. A discussion on the list of attendees should take place at the PS&E.) |
08.12.2016 | 108-150 PUBLIC RELATIONS COORDINATOR: Provide a public relations and information coordinator. The coordinator cannot be the project superintendent or construction foreman. The coordinator should be knowledgeable in construction operations, be able to develop effective media releases, possess written and verbal communication skills, and be able to organize productive meetings. Provide the name, work address, and work phone number to the relevant project, community, and media personnel. The public relations coordinator is responsible for providing the following:
|
10.31.2016 | 108-500 TERO COORDINATION: Invite the Tribal TERO Office to the Preconstruction Conference. (Use this note when working on any of the reservations.) |
Standard Notes (Design):
- Section 100
- Section 200
- Section 300
- Section 400
- Section 500
- Section 600
- Section 700
- Section 800
- Section 900
Download Template
The following template can be used for standard and plan notes.
- Design Notes (DOCM, 70K)