Plan Notes (Design) Section 500 - Rigid Pavement
Date |
Description |
03.28.2019 | 550-P__ STORM SEWER CASTINGS: Install storm sewer castings while the concrete is still in a plastic state and in a manner that does not create additional joints in the pavement, which were not part of the designed joint layout.
Install inlet castings that are adjacent to the concrete roadway concurrently with the driving surface paving operation.
Install manhole castings that lie within the limits of the concrete pavement with the paving operation. Install castings 1/4 inch to 3/8 inch below the finished pavement surface.
If installing a casting after the paving machine has passed, use vibratory methods to consolidate concrete placed or disturbed as part of the casting installation.
Include all costs for this work in the price bid for the concrete paving items.
Include on all projects with concrete paving that have storm sewer castings within the pavement or curbline. | 10.03.2014 | 550-P__ CONCRETE PAVEMENT: The development of a maturity curve, as specified in Section 550.04 B, "Mix Design", will not be required. |
|
|