Plan Notes (Design) 104 - Scope of Work
Date |
Description |
08.03.2021 | 104-P__ WATER LEVEL: The Contractor should be aware that the water levels on this project are expected to change. NDDOT reserves the right to change roadway profiles, grades, and any other aspect of the work that are affected by changing water levels.
It is the responsibility of the Contractor to become informed regarding the anticipated water level at the time of construction. The submission of a proposal will be considered conclusive evidence that the bidder is satisfied with the conditions to be encountered in performing the work and as to the requirements of the proposed work. For the purposes of preparing these plans, the water elevation was assumed to be XXXX.XX.
Typically used on grade raise projects or grade widening projects that restore clear zones due to rising water levels. |
|
|