09.26.2014 | 100-P__ COORDINATION OF PROJECTS: Another project in the vicinity of this project is under contract during the ____ construction season. This project is __________ and is located at _____________. This note can be modified to add additional construction years and project details as needed. |
08.03.2021 | 104-P__ WATER LEVEL: The Contractor should be aware that the water levels on this project are expected to change. NDDOT reserves the right to change roadway profiles, grades, and any other aspect of the work that are affected by changing water levels. It is the responsibility of the Contractor to become informed regarding the anticipated water level at the time of construction. The submission of a proposal will be considered conclusive evidence that the bidder is satisfied with the conditions to be encountered in performing the work and as to the requirements of the proposed work. For the purposes of preparing these plans, the water elevation was assumed to be XXXX.XX. Typically used on grade raise projects or grade widening projects that restore clear zones due to rising water levels. |
08.01.2023 | 107-P__ MAINTAINING TRAFFIC – UNEVEN SHOULDER: If a shoulder and the adjacent lane are uneven due to milling or paving operations, the requirements of Section 704.04 O, "Traffic Control for Uneven Pavement" apply. If the uneven shoulder and adjacent lane are due to other circumstance, the contents of this note apply.
If, at the end of the work-day, drop-offs greater than 2 inches and less than 18 inches or slopes steeper than 4:1 exist between the edge of a traffic lane and the outside edge of the proposed roadway, perform one of the following actions:
Install stackable vertical panels that meet the requirements of Section 704.03 H, "Stackable Vertical Panels", along the edge of the driving lane closest to the wedge. The Engineer will measure stackable vertical panels as specified in Section 704.05, "Method of Measurement" and will pay for panels as specified in Section 704.06, "Basis of Payment". The Engineer will not measure material used to construct the wedge. Include the cost of materials, equipment, labor, and incidentals required for this operation in the price bid for aggregate or earthwork pay items. If a 4:1 or flatter wedge is not installed, provide 24 hour flagging or pilot car operations and associated traffic control at no additional cost to the Department. (Use for widening, turn lanes, full depth reclamation, or projects with grading where drop-offs may exist. Determine which item, aggregate or earthwork, best fits the project. If a project has both, use the aggregate items; otherwise choose whichever item the project will use.) Updated for 2022 Standard Specifications |
Plan Notes (Design):
- Section 100
- Section 200
- Section 300
- Section 400
- Section 500
- Section 600
- Section 700
- Section 800
- Section 900
Download Template
The following template can be used for standard and plan notes.
- Design Notes (DOCM, 70K)